Metropolitan State University

ICS 325

 

Sample Project Plan

 

Come up with 30-50 intermediate goals or tasks along with a date by which you plan to complete each.  In addition, estimate the time it will take to perform each task.  As you work, record the time you spend.

 

 

Goals

Estimated

Time in Hours

Actual Time

Deadline

Actual Completion Date

Project description

.5

1.0

July 22

July 21

Architectural design

7

8.25

July 26

July 27

Database design

10

7.25

July 28

July 28

 

 

 

 

 

etc.

20

40

 

 

 

 

 

 

 

 

 

 

 

 

Prepare Presentation

2

5

August 11

August 12

Final Report

1

10

August 11

August 12

 

 

 

 

 

Total Time

40.5

71.5